|
UNEV will be an interstate common carrier Pipeline and will be
constructed and operated under oversight of the U.S. Department
of Transportation and Office of Pipeline Safety. UNEV will also
follow the regulations established by the Environmental Protection
Agency and other federal and state regulatory agencies.
Members of the UNEV project team have worked with the U.S. Bureau
of Land Management, the lead agency on the project, to look at alignment
options and construction considerations. We have also conducted
extensive environmental studies to comply with the National Environmental
Policy Act (NEPA) and various other federal, state and local environmental
regulations. As part of this process, stakeholders and the public
have had the opportunity to comment on the project. For more information
about the NEPA process or the public scoping meetings visit http://www.blm.gov/ut/st/en.html.
As a long-time steward of the environment and as a good corporate
citizen, Holly Corporation has led the UNEV project team to design
a construction process that takes into account the special needs
of various sections of the Pipeline. Holly has also worked with
the UNEV project team and the U.S. Bureau of Land Management to
put in place a comprehensive plan of development.
The construction of the UNEV Pipeline for the most part will be
the conventional trenching process, however in some areas a horizontal
directional drill or bore will be used to go under roads and waterways.
Holly has worked with the UNEV project team and the U.S. Bureau
of Land Management to put in place a plan to restore and revegetate
the area when finished.
Holly is taking much care to ensure UNEV will be constructed and
operated in a safe manner. The Pipeline will be constructed under
the stringent guidelines required by the U.S. Department of Transportation.
The 400-mile, buried UNEV Pipeline will be 12-inch diameter welded
steel. All pipe used will meet the industry’s standards set
by the American Petroleum Institute. Each weld will be x-rayed and
before going into service the entire Pipeline will be pressured
tested with water at a pressure that is at least 125 percent of
the maximum operating pressure.
 |
| Bi-directional pipeline pig |
The pipe will be coated using fusion-bonded epoxy or another suitable
coating as recommended for the soil conditions to inhibit external
corrosion. The Pipeline will also be under cathodic protection,
an electrical means to inhibit corrosion, which is a secondary level
of corrosion protection.
An internal inspection tool, called a smart pig, will be used to
measure metal loss due to corrosion or third-party damage on a periodic
basis. Corrosion coupons will be installed at each end of the Pipeline
to monitor any corrosive activity. If required, corrosion inhibitor
chemicals will also be injected at the Pipeline’s origin.
Surface and aerial patrols will occur every other week or at least
26 times a year. These patrols will monitor for any third-party
encroachment, right-of-way condition and the condition of the line
markers and above ground valves.
Holly’s control center will monitor the flow and pressure
of the Pipeline 24 hours a day, seven days a week. If all communications
are lost for more than one minute the Pipeline will shut down. Holly
provides training to all local employees to perform the duties of
a first responder. The duties emphasize protection of the public
first followed by the protection of the environment.
|